Weds OCT 5th – Critical Path Analysis

LEARNING OBJECTIVE: To Understand how to use networks to show the flow of activities within a project

SUCCESS CRITERIA: You Will. Understand and be able to use dependency diagrams and be able to represent related activies of a project as a connected network

KEYWORDS: Dependency Diagram, Dummies, Source Node, Sink Node (Tail Node), Forward Pass, Backward Pass, Early Event, Late Event

LESSON: Work through this Lesson with students, using last three screens as examples for students to work through.

Now use this lesson to show the use of Dummies, again use last three screens to give students lots of practice

Ex 4A can now be completed, first exercise towards this weeks homework.